ASN’s supervision of the Flamanville-3 reactor construction (EPR) : latest news
Following a period of preparatory work that began in summer 2006, construction on the Flamanville 3 European Pressurized water Reactor (EPR) project began in September 2007.
Since the end of 2007, construction work has continued on various buildings at the Flamanville 3 site, including, in late 2010, the following activities:
- reactor building: concreting work on the internal structures, erection of the vertical section of the metal liner of the inner containment wall, continuation of reinforcement and concreting work on the outer containment, and final concreting of the cylindrical part of the outer containment wall;
- other structures in the nuclear island (fuel storage buildings, safeguard auxiliary buildings, emergency diesel generators, etc.): reinforcement and concreting operations have continued on buildings in addition to continuing work on electrical and mechanical assembly;
- operational service centre: finishing work performed in roofed-in areas and electrical assembly completed;
- turbine hall: work continues on installation of components such as the condenser and assembly of steam lines;
At the Flamanville 3 worksite, ASN performed 8 inspections in 2007, 14 in 2008, 24 in 2009 and 24 in 2010. More than two thirds of inspections carried out in 2010 concern technical issues relating to progress at the site and current activities (civil engineering, mechanical assembly and electrical systems). Other inspections concern general issues (management of safety, quality in the context of the order of 10 August 1984, organisational and human factors, emergency resources, worksite impact on neighbouring reactors in operation, contractors, etc.).
ASN is also responsible for labour inspection. During the third and fourth quarters of 2010, there were six inspections of safety and working conditions. In particular, issues regarding dust and compliance with access to the various workstations were examined. The labour inspector also attended technical meetings on worksite activities and the December meeting of the combined enterprise group on safety, health and working conditions. On 24 January 2011, following the deadly fall of a worker at the inner containment wall worksite of the reactor building currently under construction, two labour inspectors from ASN visited the site as part of their investigation. Exact circumstances of the accident are being examined.
In addition, ASN inspected engineering departments responsible for construction and monitoring of detailed design studies and monitoring qualification and manufacturing efforts. In 2010 ASN performed nine inspections of EDF engineering departments including five that were carried out in the workshops and offices of manufacturers of safety-related systems and components.
In 2010, ASN and its approved inspection bodies spent the equivalent of nearly 1,300 days in the workshops of AREVA NP and its subcontractors performing nearly 900 manufacturing inspections on nuclear pressure equipment that constitutes the reactor coolant and secondary systems.
-
Supervision of the EPR reactor: Information notice No. 10
02/10/2011 5:21 pm
Information notice No 10: ASN continues inspections at the EPR Flamanville reactor construction siteDuring the second half of 2010, ASN continued its inspection activities at the Flamanville 3 EPR construction site.
-
Supervision ot the EPR reactor : information notice No 9
08/27/2010 5:58 pm
Information notice No 9: Despite delays at the worksite, ASN has maintained the same pace of inspection as in 2009.During the second quarter of 2010, ASN continued its inspection activities at the Flamanville 3 EPR construction site.
-
Supervision of the EPR reactor: Information notice No. 8
06/11/2010 12:38 pm
Information Notice No. 8: ASN continues inspections on the EPR Flamanville reactor construction siteThe French Nuclear Safety Authority (ASN) continued its inspections on the EPR Flamanville reactor construction site during the first quarter of 2010, and found work to be progressing in good order. Several issues are noteworthy.
-
Supervision of the EPR reactor : Information notice No.7
02/02/2010 6:00 am
Information notice No.7: Progress in ASN inspections of construction activitiesDuring the second half of 2009, ASN continued its inspection activities on the Flamanville 3 EPR construction site.
-
Information notice No. 6: ASN remains vigilant and is pursuing its inspect ...
07/31/2009 5:52 pm
Information notice No. 6: ASN remains vigilant and is pursuing its inspection programme at the Flamanville 3 EPR site
Newsletter No. 6: ASN remains vigilant and is pursuing its inspection programme at the Flamanville 3 EPR site
-
Information notice No.5: ASN keeps a close watch on construction work ...
02/12/2009 5:50 pm
Information notice No.5: ASN keeps a close watch on construction work on the future Flamanville 3 reactor
Information notice No.5: ASN keeps a close watch on construction work on the future Flamanville 3 reactor
-
Information notice No.4: ASN continues to implement its inspection ...
09/11/2008 5:48 pm
Information notice No.4: ASN continues to implement its inspection programme on the Flamanville 3 EPR site
Information notice No.4: ASN continues to implement its inspection programme on the Flamanville 3 EPR site
-
Information notice No.3: ASN authorises the resumption of concrete pouring ...
06/19/2008 5:46 pm
Information notice No.3: ASN authorises the resumption of concrete pouring work on the EPR site
Information notice No.3: ASN authorises the resumption of concrete pouring work on the EPR site
-
Information notice No.2: ASN asks EDF for tighter control on construction work
06/02/2008 5:43 pm
Information notice No.2: ASN asks EDF for tighter control on construction work
Information notice No.2: ASN asks EDF for tighter control on construction work
-
EPR Reactor: Information notice No.1
04/29/2008 5:32 pm
EPR Reactor: Information notice No.1
EPR Reactor: Information notice No.1